Ciba-Geigy Superfund Site Remediation

Daily Report

(What is a Daily Report?)

 

For air monitoring data and work performed on:

Tuesday

March 9, 2010

 

Information is updated by noon (EST) of each workday.

Prior Daily Reports are archived on the CALENDAR page.


Activity Description

On 03/9/10, routine activities at the site began at 7:00 am.

Air monitoring activities were conducted in accordance with the approved  Air Monitoring Plan.

A total of approximately 600 cubic yards of soil were excavated from the DDA and 900 cubic yards from the FCD. The excavated material was taken to the Ex-Situ Biotreatment Buildings in accordance with the approved Ex-Situ Biotreatment Plan.

 